Countdown to MVP Launch
Target window: October 2026 · committed deadline 31 Oct 2026
--
Days
--
Hours
--
Minutes
--
Seconds
⏱ -- working weeks left · launch builds every day from here
12%
plan complete
5 / 23
sprints done
198
items shipped
18
sprints left
--
weeks in so far
📍 Where we are on the road
Jan 2026 · kickoffTodayOct 2026 · launch
✓ What we've done (Sprints 1–5)
AWS infra + crawlers online; 2-year Facebook backfill for every pilot page
Data warehouse + standard tables built
5 post-level NLP models live (sentiment, emotion, topic, intent, toxicity)
Comment MTL DeBERTa model trained + gold set
App shell + login + 5 pages with real signals
CI/CD + infrastructure-as-code baseline; OAuth groundwork
End-to-end pipeline test (text + image + alerts)
→ What's left to launch (Sprints 6–23)
Image / video understanding on posts (S6–7)
Draft virality scoring + post traction (S8–9)
Crisis detector + alerts engine (S11)
The 7 MVP surfaces wired to live data
Art-E grounded Q&A — tool-use + citations (pulled forward)
Production hardening — the 5 pillars + scale test
Facebook OAuth Live-Mode flip → 5 pilots live (the final task)
🚀 Route 1 · Faheem full-time + new AI engineer
~22 Sep 2026
projected arrival · ~5–6 weeks buffer before the deadline · ~£3k/mo
⚡ Route 2 · Only Faheem full-time
~18 Oct 2026
projected arrival · ~2 weeks buffer · lowest cash · ~£2k/mo