✓ Approved · 12 June 2026
The network moved into the MVP
Zero scope cuts · compensated by capacity + process · full detail in the sprint tracker and master plan
+28
network tickets moved
into the MVP build
0
tasks cut · everything
already planned still ships
28 Nov
launch unchanged
2 days of headroom
Before → after
Before · 11 Jun66 MVP60 LATER
MVP · launches 28 Nov
AnalyticsPredictionArt-E Q&ACrisis & AlertsBest TimesReportsDiscovery · view-only preview
Phase 2 · someday
Cross-page graphMatch algorithmDiscovery v1Business cardsArt-E collabsGraph research
Fast-Track
Health ScoreBriefingsno Instagram
→
After · approved 12 Jun69 MVP57 LATER
MVP · still launches 28 Nov +28 tickets
AnalyticsPredictionArt-E Q&ACrisis & AlertsBest TimesReportsDiscovery · full v1Cross-page graphMatch algorithmBusiness cardsArt-E collabs
Phase 2 · research only now
Graph-of-graphsGraphSAGECross-client intel
Fast-Track
Health ScoreBriefingsInstagram · week +1
Where the new work landed · Sprints 6 → 23 · owner Muteeb
⚡
How we pay for itMuteeb owns the slice · graph starts now · QA batched from S14 · S10+S12 merged
CAPACITY, NOT CUTS
28 Nov 2026launch · unchanged